LSAT Chorrera – El Torno

– March 2018

The construction of the underground line of high-voltage 115 kV line between the La Chorrera Substation and Substation El Tomo, belonging to the network of EDEMET, is part of the project of modernization of the electrical distribution system which has been conducted in the Republic of Panama and that on this occasion will favor the province of Panama.

 

This new infrastructure, in addition to contributing to the growth in the area, with the underground cables are typically looking for the reduction of outages by causes beyond the control of the network, reducing the rate of accidents and reduces the visual impact of the urban space.

Izharia was in charge of the engineering of this project and is currently doing the monitoring and audit of this work, which has a 90% advance in Civil Works and is estimated to be completed by June 2018.