LAT 220 Kv Dc - SC Valle 1 Y 2 - SE Renedo Promotores - SE Las Arroyadas C. Seccionamiento

The evacuation lines of the PSFV Valle 1 and Valle 2 plants consist of two 220 kV circuits, the designation of which shall be as follows:

The lines are planned to run underground throughout their entire length, with a total length of 48.256 km. In general terms, the installation can be divided into three sections, depending on the number of circuits running along the route.

The first section originates at substations SE PSFV Valle 1 and 2, with each substation initiating single-circuit trunking from each substation. Subsequently, both circuits share double-circuit trunking up to a point from which both circuits branch off.

Section 2 starts after leaving the point indicated above and ends at SE Renedo Promotores. This section consists of a single circuit, previously named LAT 220 kV SE Valle 1 - SE Renedo Promotores. The length of this section is 1.160 km.

Section 3 corresponds to the continuation of the LAT 220 kV SE Valle 2 - CS Las Arroyadas single circuit line. It starts at the aforementioned point and ends at the Las Arroyadas substation. It is 17.395 km long.

In both the single-circuit and double-circuit sections, there will be one string per line with cables in a staggered configuration. The cable used will be RHZ1-RA-+2OL(AS) 127/220 (245) kV 1X630mm2 Al + H315 (Cu) type.

Date:
LOCATION:
Valladolid, España
END DATE:
2024
INDUSTRY:
Energy
PROJECT DESCRIPTION:
Construction of the 220 kV evacuation lines for the Valle 1 and Valle 2 PSFV plants in Valladolid, Spain.